From Development Order to Certificate of Completion

Securing authority permits and approvals is a critical process for any development or construction project in Malaysia. For foreign investors—such as Japanese companies—understanding these procedures is essential, as they differ significantly from those in other countries. While each Malaysian state may have slight variations, the overall framework follows a general guideline.

This article provides a detailed roadmap of the key stages involved in obtaining project approvals in Malaysia, from initial planning to final certification.


1. Data Gathering Process

Preparation begins approximately one month before applying for a Development Order (DO). This stage involves collecting essential information and drafting preliminary designs to ensure compliance and avoid delays later.

Key activities include:

  • Consultants (town planner, architect, C&S engineers, M&E engineers) gather data and prepare basic development designs.
  • Confirm land matters such as: 
    • Ownership
    • Amalgamation and subdivision
    • Rezoning
  • Obtain information from utility providers (power, water, network services).
  • Ensure sufficient resources within the development area and compliance with land usage regulations.

This proactive approach minimizes risks of obstacles during the lengthy approval process.


2. Planning Approval Process

The Development Order (DO)—locally known as Kebenaran Merancang (KM)—is the foundation of all subsequent approvals. Without a DO, no other applications can proceed.

Timeline: Approximately 4 months from submission.

Process Overview:

  • Led by a Principal Submitting Person (PSP) —usually a town planner, but sometimes an architect or engineer depending on the project type and state requirements.
  • Online submission via the City Council’s One-Stop-Center (OSC) portal.
  • Hardcopy submission to the Planning Department after OSC clearance.
  • Plans are circulated to relevant departments and agencies for review.
  • Site visits and public display for feedback.

Additional Submissions (as required):

  • Environmental Impact Analysis (EIA) – Department of Environment (DOE)
  • Traffic Impact Analysis (TIA) – Engineering Department
  • Road Safety Audit (RSA Stage 1 & 2) – Public Works Department (JKR)
  • Water Enactment Report – Department of Irrigation & Drainage (DID/JPS)

Approval is granted only if there are no objections from departments, agencies, or the public.


3. Design Approvals

After obtaining the DO, consultants proceed with Building Plan (BP) submissions to technical departments.

Main Approvals:

  • Building Department – City Council
  • Engineering Department – City Council
  • Fire & Rescue Department (BOMBA) – Passive Fire Protection System approval is mandatory before BP approval.

Supporting Submissions:

  • Structural design, road & drainage, street lighting, sanitary systems, and earthworks – Engineering Department
  • Landscape proposals – Landscape Department
  • Sewerage approvals (PDC1 & PDC2) – Indah Water Konsortium (IWK)
  • Internal & external water supply – Water service provider
  • RSA Stage 3 – JKR

Timeline: BP approval typically takes up to 4 months.


4. Works Commencement Permits

Before construction begins, a Works Commencement Permit is required.

Timeline: About 1 month after BP approval.

Key Requirements:

  • PSP submits a Notification for Works Commencement via OSC.
  • Clearance from technical departments (engineering, building, IWK, etc.).
  • Temporary site hoarding approval – Building Department.
  • Applications for temporary facilities (workers’ quarters, site office, toilets, canteen).
  • Separate applications for temporary utilities (power, water, network).
  • Tree felling permits – Landscape Department.

5. Construction Stage

During construction, several additional approvals are necessary:

  • Active Fire Protection System – BOMBA Mechanical Division.
  • If Fire Engineering Performance-Based Approach is required, submit before Active Fire Protection approval.
  • Amendment Building Plan (ABP) – Submit revised plans based on BOMBA approval before requesting final inspection.

Other submissions include:

  • Power connection
  • Water tapping
  • Sewerage approvals (PDC3–PDC8)
  • RSA Stage 4 & 5

6. Final Inspection & Certificate of Completion and Compliance (CCC)

The CCC signifies that the building complies with approved plans and safety standards. It is mandatory for all buildings—residential, commercial, or industrial—before occupancy.

Issued by: PSP (architect or engineer).
Timeline: The final inspection and CCC issuance process typically takes around 3 months.

Process:

  • PSP ensures all technical conditions are met.
  • Stage 1 final inspections with relevant departments and agencies.
  • Collect all Form Gs as supporting documents.
  • Stage 2 final inspection by City Council’s Building Department.
  • PSP issues CCC and deposits it with OSC, Building Department, and professional boards (e.g., Board of Engineers Malaysia).

At this point, the building is officially fit for occupation.

Conclusion

Navigating Malaysia’s authority approval process—from Development Order to Certificate of Completion and Compliance—requires expertise, precision, and familiarity with local regulations. For foreign investors, partnering with an experienced contractor is key to ensuring compliance and avoiding costly delays.

As a Japanese construction company established in Malaysia since 1971, holding the CIDB Malaysia G7 contractor license and certified with ISO 9001:2015, we have decades of experience working with Malaysian authorities and understanding their requirements. Our proven track record makes us the best choice for foreign investors seeking a reliable partner for successful project delivery in Malaysia.